Road Drainage Works Program

17 MAY 2024

Taylors Arm Road, Taylors Arm

Shoulder and drainage works have progressed along Taylors Arm Road from Taylors Arm township to the end of the sealed section at the intersection with Naylors Lane, Upper Taylors Arm. These works are anticipated to take around 2 weeks, weather permitting.

Please take care when driving in and around the work site, there will be 2 machines at work at any given time.

Wilson Road, Bowraville

Shoulder and drainage works will commence on Wilson Road, Bowraville on Monday 20 May.

Starting in Bowraville and heading to Macksville, these works are anticipated to take around 2 weeks, weather permitting.

Please take care when driving in and around the work site.

10 MAY 2024

Taylors Arm Rd, Macksville

Shoulder and drainage works on Taylors Arm Rd are due to commence on Monday 13 May, weather permitting.
Works will begin in Macksville and progress along Taylors Arm Rd in the direction of Taylors Arm.
Please take care and exercise caution when driving in and around the work site.

Bellingen Rd, Bowraville

Shoulder and drainage works on Bellingen Road have progressed onto Helliwells Road and Missabotti Road towards Missabotti.
Weather permitting, it is anticipated that works will be completed along these roads by the end of next week.
Please take care when driving in and around the work site.

Valla Road, Valla

Shoulder and drainage works on Valla Road are nearing completion.
Completion is anticipated by the end of business today - Friday 10 May.
Please take care when driving in and around the work site.

North Arm Rd, Bowraville

Shoulder and drainage works on North Arm Road will continue next week, weather permitting.
Please take care when driving in and around the work site.

South Arm Rd, Bowraville

Shoulder and drainage works on South Arm Road will continue next week, weather permitting.
Please take care when driving in and around the work site.

30 APRIL 2024

South Arm Road, Bowraville

Shoulder and drainage works will be commencing Tomorrow Wednesday 30 April on South Arm Road.
Works will begin from Bowraville heading out to the extent of the sealed road section.
Please slow down and exercise caution when driving in and around the work site

29 APRIL 2024

North Arm Rd, Bowraville

Shoulder and drainage works will be continuing from Monday 29 April on North Arm Road, Bowraville.
Please slow down and exercise caution when driving in and around the work site.

Valla Road, Valla

Shoulder and drainage works will be commencing Monday 29 April on Valla Road, Valla.
Works will begin from Giinagay Way heading outwards on Valla Road.
Please slow down and exercise caution when driving in and around the work site.

Bellingen Rd, Bowraville

Shoulder and drainage works will be commencing Monday 29 April on Bellingen Road, Bowraville.
Works will begin at the start of Bellingen Road heading in the direction of Missabotti.
Please slow down and exercise caution when driving in and around the work site.

24 APRIL 2024

Council are planning to undertake road drainage works in the Bowraville, Missabotti, Yarranbella, Taylors Arm and Valla area’s in the upcoming months.

These activities will include works on North Arm Road, South Arm Road, Valla Road, Bellingen Road, Boat Harbour Road, Taylors Arm Road, Wilsons Road, Missabotti Road and Helliwell’s Road.

Council asks the community to please be aware of these activities and use caution when passing through the sites.

Traffic control and signage will be in place during the works for the safety of the community and minor delays may be encountered during this period.

Further updates will be provided during these works and Council appreciates the communities patience until the project is completed.

For further information, please contact Council’s Disaster Recovery Team Ph:6568 2555 or at Disaster.Recovery@nambucca.nsw.gov.au

14 OCTOBER 2024

Council’s Maintenance Grading Team have commenced maintenance works to the Newee Creek area starting at Gordons Knob Road.

The Team will move to Tewinga and Valla within the month, weather permitting.

7 NOVEMBER 2024


Council’s Maintenance Grading Team have completed works in the Newee Creek Area and have moved to Valla.

Council’s Construction crew will undertake maintenance grading activities at Tewinga between heavy patching works in the Newee Creek Area.

The grading team will move to Allgomera Road, Congarinni Road South and Taylors Arm Road (South Bank) sequentially after maintenance works are completed in the Valla Area.